Roquette 110kV booster Station project(The content illustration is the same as the cover drawing)
 
(The content illustration is the same as the cover drawing)
Rogate (China) Fine Chemical Co., Ltd. is located in Songjiang Industrial Zone, Lianyungang Economic and Technological Development Zone, and 110kV buck station is located in the middle of the factory. The main transformer is 1× 31.5mVA in current phase, and the prospect (1×31.5+2×20) is MVA. 110kV incoming line prospect 2 times, this period 2 times; Main transition line prospect 3 times, this period 1 time.